The roadway work started back up this week with the sign structure base being installed west of the tracks. Surveyors were also on site laying out the curb and gutter (pink flags) with the curb installation starting Monday.
Roadway Schedule (Weather Dependent)
- Week of June 9 – Drill/pour overhead sign structure concrete base, stake out curb and gutter, bring gravel to correct height. (Ongoing)
- Week of June 16 – Begin Curb and Gutter, sidewalk.
- Week of June 23 – Prep/asphalt pave the site.
Traffic:
- Access to Dollar General can be made by taking WIS 20 west across County ES, using the median opening for Shell/McDonalds/Culvers, and going west on the WIS 20 EB lanes.
- Access to Shell/McDonalds/Culverts can be made using WIS 20 west across County ES to the median opening for the left turn like the current configuration. There are other accesses off County ES as well that will stay open.
- Access to the Oak Ridge Cemetery is available by using WIS 20 WB lanes.
- The I-43/WIS 20 interchange will remain open
- County ES will remain open but the right turn lane for County ES SB to WIS 20 WB will close for sidewalk and grading.
Other nearby projects:
Information about the US 12 project between Whitewater and WIS 20/WIS 67: