08-21-2026 Beulah Heights Culvert Update-


This Week:
🚧 Culvert Assembly is COMPLETE!!
🚧 Construction Meeting 8/20: The Culvert is fully Assembled. All 3,500 bolts are in place and our 45,000 lb Culvert will be tripple checked Friday and ready to be placed.

Next Week:
🚧 Crews will be measuring to be sure that the area is still to grade after today's storms on Monday.
🚧 Weather Dependant- The Culvert will be placed early next week. Keep an eye out for the massive crane's arrival.
🚧 Dirty water dewatering continues.
There will be weekly construction meetings (Thursdays) and Updates Posted on the Town Website and Facebook each Friday. Subscribe to the Town website to keep up with the latest information.

 