08-07-2026 Beulah Heights Culvert Update-
08-07-2026 Beulah Heights Culvert Update-
This Week:
There has been a lot of progress this week.
🚧 Excavation continued.
🚧 More sheeting installed
🚧 Excavation brought to grade (Thursday PM)
🚧 Dirty Water-dewatering (Friday)
🚧 Construction Meeting 8/7: We are proceeding with the third of three options. This option allows for a shorter installation schedule than the other two options. It will involve assembling the culvert on the road and lowering it into place with a crane. This operation will be performed while some water remains in the work area, where the other options would have required complete dewatering and a curing time for cementitious materials. With this option, assembly of the culvert is scheduled to start early next week depending on weather.
📁Dan Meier (Lynch) Andy (RLP) and Craig (DNR) met after the construction meeting. A dewatering plan was agreed upon and will begin Friday.
Next Week:
🚧 They will begin constructing the culvert (weather dependent, storms expected Monday)
🚧 Dirty water dewatering continues
There will be weekly construction meetings (Thursdays) and Updates Posted on the Town Website and Facebook each Friday. Subscribe to the Town website to keep up with the latest information.