This Week:
🚧 Excavation Week!
🚧 The Village's 4" pump was returned to them (Than you)
🚧 6" Pump Added and Running along with 24/7 Electric Pump
🚧 Well Created on the Lake Side
🚧 Dirty Water Dewatering
🚧 Measurements and Offsets re-taken by Lynch (Friday)
🫣Unstable Soil Conditions Were Discovered During Excavation, digging had to stop to preserve the roadway edges and neighboring driveways. Additional sheet piling will need to be installed to preserve them. On Friday, the Project Foreman was working to secure sheeting and get a cost estimate based on the measurements taken by Lynch Friday. I will make an additional post once we have more information from the supplier.
Next Week:
🚧 Excavation on Hold Until Sheeting is Delivered/Installed
🚧 Working to Draw Water Down To Before Project Levels
🚧 Additional Sheet Piling to be Delivered/Installed
🚧 Excavation Week Continues once Sheet Piling is Installed
🚧 Dirty Water Dewatering
🚧 Continue Additional Bypass Pumping as needed 🌧️
⚠️ Please slow down when diving down the temporary road and show empathy for the workers who are doing their best to complete this complex job as efficiently as possible while navigating unforeseeable setbacks. Collaboration with the Contractor, Town DPW, Lynch and The DNR will continue as we navigate these unforeseen challenges as efficiently as possible.
There will be weekly construction meetings and Updates Posted on the Town Website and Facebook each Friday. Subscribe to the Town website to keep up with the latest information. *Text messaging notifications available*