This Week:

Sheet Piling readjusted on the inland side 6/11

4-Inch Bypass Pump Installed on Monday

Dewater and Excavate as able

Temporary Road widened by the Contractor (Thanks Andy!)

Monitoring Water Depth including DNR Visit


Due to the Rain Wednesday and Thursday a Fourth 3-inch Pump was added and a 4-inch pump was borrowed from the
Village of East Troy to also be added Thursday prior to the storm.

Todd and our DPW Team will be pumping 8-10 inches below normal water line over the weekend
Please know our trusted team is monitoring the situation and individual phone calls/text messages from residents regarding water height that are not an emergency are not needed.
Next Week:

24 hour Electric Pump Installed and Running

Culvert and Roadway will be Removed on Monday

Temporary Bypass Road in use beginning Monday

Pulling Mud from the Lake Side

Further Dewater and Excavate

Backwater Challenges have lengthened the process and new mitigation strategies are evolving as the need arises.

Continue Additional Bypass Pumping as needed


Please slow down when diving down the temporary road and show empathy for the workers who are doing their best to complete this complex job as efficiently as possible while navigating unforseeable setbacks. Collaboration with the Contractor, Town DPW, Lynch and The DNR will continue as we navigate these unforeseen challenges as efficiently as possible.
There will be weekly construction meetings and Updates Posted on the Town Website and Facebook each Friday. Subscribe to the Town website to keep up with the latest information. *Text messaging notifications available*