06-05-2026 Beulah Heights Culvert Update-

This Week:
🚧 Sheet Piling Completed on the Lake Side Wednesday  5/3
🚧 Temporary Road in Use- take it slow
🚧 Channel Side Sheet Piling Placed on Thursday 5/4
The channel side has a much softer bottom and sheets had to be welded together while in the water to hold the depth and shape needed. The on the spot problem solving for this project has been impressive to watch. Andy and his Team are Top Shelf!
🚧Monitored Water Depth
🚧Daily Pumping
🌧️Due to the Rain Friday Three Pumps are Running. Todd and our DPW Team will be keeping them running as needed through out the weekend. Please know our trusted team is monitoring the situation and individual phone calls/text messages from residents regarding water height that are not an emergency are not needed.
Next Week:
🚧 24 hour Electric Pump Installed and Running
🚧 4 Inch Bypass Pump Install on Monday
🚧 Pulling Mud from the Lake Side
🚧 Dewater and Excivate
🚧 Widening the temporary Road slightly
🚧 Continue Additional Pumping as needed 🌧️
⚠️ Please slow down when diving down the temporary road and show empathy for the workers who are doing their best to complete this complex job as efficiently as possible while navigating unforseeable setbacks.
There will be weekly construction meetings and Updates Posted on the Town Website and Facebook each Friday. Subscribe to the Town website to keep up with the latest information. *Text messaging notifications available*

Staging Making the Temporary Road Wider

Staging Making the Temporary Road Wider

Lake Side Done

Getting Ready For Channel Side Welding

Channel Side

Thursday Flow

Hooking it Up

Clean Water Area

Beauty in the Construction

Friday Morning Pumping due to Rainfall

All 3 pumps going!