This Week:
Lynch will be staking off the area for the temporary roadway.
WE Energies (Miller) moved the gas lines.
Gravel was brought in and put in place for the temporary roadway.
Next Week:
Single lane traffic will begin on the temporary roadway.
Temporary Road instillation.
Sheet Piling installation to dam waterway begins.
There will be weekly construction meetings and updates on the Town Website and Facebook. Subscribe to the Town website to keep up with the latest information. *Text messaging notifications available*