Please ensure Javascript is enabled for purposes of website accessibility
Notice 03-21-2025 : Your Easy Access to Up-to-Date Information—Explore our new site, designed to make your search simple and straightforward.

04-24-2026 Beulah Heights Culvert Update-

 
This Week:
 🚧 Monday and Tuesday (4/20-4/21)
Lynch will be staking off the area for the temporary roadway.
 
🚧 Wednesday and Thursday (4/22-4/23)
WE Energies (Miller) moved the gas lines.
 
🚧 Friday (4/24)
Gravel was brought in and put in place for the temporary roadway.
 
Next Week:
‼️HARD CLOSURE of the roadway and waterway is scheduled for April 27, 2026
 
🚧 Monday (4/27)
Single lane traffic will begin on the temporary roadway.
 
🚧 Tuesday - Friday (4/28 - 5/1)
Temporary Road instillation.

🚧 Possibly Friday (5/1)
Sheet Piling installation to dam waterway begins.
 
There will be weekly construction meetings and updates on the Town Website and Facebook. Subscribe to the Town website to keep up with the latest information. *Text messaging notifications available*