The county line area is getting close to finishing and the work in East Troy was delayed a week as the concrete crew was stuck on another project. Hopefully, they will make up lost ground next week and we can start removing the drums and other traffic control devices.
The work for the culvert east of Carver School Rd is scheduled for November 4th. This will result in a closure of WIS 20 between Carver School and Hillburn Mill Rd for about a week while we replace the culvert. We will have message boards directing traffic around the closure to help keep local access.
East Troy – WIS 20/County ES intersection
- Finish up the concrete islands in the intersection
WIS 20 – Bell School Road to Honey Creek Rd (County Line area)
- This part of the project will decide when we are able to re-open WIS 20 between East Troy and Waterford. Below are the remaining operations that need to occur.
- Install new guardrail along the north side of WIS 20 (the Honey Creek side) – Ongoing
- Install Rumble Strips, Pavement Markings, and Signage (Week of 10/28 but weather dependent)
WIS 20 from County L to WIS 83 (minus the County Line area)
- Complete most everything we can ahead of the other areas so when the longer duration sections become available, we can turn things around faster. Most of this stretch looks finished, but since we cannot reopen WIS 20 until the county line area is completed it will look like not much else is happening.
WIS 20 (East Troy)
Traffic:
- Access to Bower’s Produce can be made by continuing east on WIS 20 from County L (East Troy)
- Access to Green Meadows can be made by going west on WIS 20 from WIS 83 (Waterford)
- Access to Culver’s will be by using WIS 20.
This Week:
- Epoxy coating applied under the I-43 bridges
Next Week:
- Pour and completed the concrete islands in the intersection.
- Begin removing some drums and barricades.
WIS 20 – County L to WIS 83 (Waterford) Traffic:
- Access to Bower’s Produce can be made by continuing east on WIS 20 from County L (East Troy)
- Access to Green Meadows can be made by going west on WIS 20 from WIS 83 (Waterford)
- Access to Witte Landscaping can be made by going west on WIS 20 from WIS 83 (Waterford)
This Week:
- Asphalt paving
Next Week:
- Continue guardrail Installation
- Pavement Markings