Generic selectors
Exact matches only
Search in title
Search in content
Post Type Selectors

Streaming Issues: Thank you for your patience last night with the LIVE Stream of the Town Board Meeting. A cable was accidentally unplugged from the camera by someone sitting in the back row. I will be working with Todd to make some changes so that meeting patrons no longer have to worry about that sort of thing. We had plans for some further changes in January, this will just become a part of that list. Stay tuned to see our progress, there may be some test streams in the next two weeks.Thank you again for your understanding 🙃 ~Jen

Construction Update WIS 20

Asphalt paving has moving along this week from Honey Creek Rd to WIS 83. That should be wrapped up on Monday and Tuesday the crews will move to the area between County L and Bell School. We have a few patches to fix up and those will be completed on Monday.

 

In East Troy we started shouldering and topsoil placement. Pavement marking and signage is scheduled for next week along with signal work. Having the markings and signing installed will allow traffic on WIS 20 to be put back on the correct side of the median and have the I-43 ramps re-opened.

 

I-43 Ramps at WIS 20 – Scheduled to re-opened on Monday, September 16th. Not sure on the exact time of day yet but will be included in next weeks update.  

 

WIS 20 (East Troy)

Traffic:

  1. Access to Bower’s Produce can be made by continuing east on WIS 20 from County L (East Troy)
  2. Access to Green Meadows can be made by going west on WIS 20 from WIS 83 (Waterford)
  3. Access to Culver’s will be by using WIS 20.

 

This Week:

  1. Shouldering along WIS 20
  2. Topsoil placement

 

Next Week:

  1. Continue Topsoiling/grading
  2. Pavement markings
  3. Seeding/restoration

 

WIS 20 – County L to WIS 83 (Waterford) Traffic:

  1. Access to Bower’s Produce can be made by continuing east on WIS 20 from County L (East Troy)
  2. Access to Green Meadows can be made by going west on WIS 20 from WIS 83 (Waterford)
  3. Access to Witte Landscaping can be made by going west on WIS 20 from WIS 83 (Waterford)

 

This Week:

  1. Asphalt paving from Honey Creek Road to WIS 83
  2. Completed milling operations removing the top 2” of asphalt

 

Next Week:

  1. Complete asphalt paving from Honey Creek Rd to WIS 83
  2. Begin asphalt paving from County L to Bell School Rd on Tuesday
  3. Begin working on the retaining wall

 

Long Term (2+weeks)

  1. Complete asphalt paving
  2. Complete the retaining wall
  3. Install rumble strips
  4. Install pavement markings
  5. Install signing

 

Information on the other WisDOT project up on I-43 from US 12 to WIS 83 is below:

https://projects.511wi.gov/12rock/

 

Information on the US 12 project between Elkhorn and WIS 20:

https://projects.511wi.gov/12elkhorn/

 

 

If you do not want to receive these updates, please let me know and I can remove you from the distribution list. Also, WisDOT has a project website set up for information that is more general than this email but could be useful if needed. https://projects.511wi.gov/20wal/