Construction Update WIS 20: CONSTRUCTION UPDATE WIS 20-We were able to snag a traffic control crew a day early and they have been working removing equipment and preparing to reopen WIS 20. The crew should be completed with their work in the next few hours and then WIS 20 will be reopened from East Troy to Waterford!Thank you all for your patience and understanding as this was a lengthy project and a lot of work to get done!

Construction Update WIS 20

All the patches from County L to WIS 83 have been filled and the extra drums and barricades will be picked up today. We started paving from the CN Railroad tracks going east to WIS 83 yesterday and will continue paving east next week.

 

In East Troy we continued sidewalk installation with topsoiling and restoration efforts starting up next week.

 

WIS 20 (East Troy)

Traffic:

  1. Access to Bower’s Produce can be made by continuing east on WIS 20 from County L (East Troy)
  2. Access to Green Meadows can be made by going west on WIS 20 from WIS 83 (Waterford)
  3. Access to Culver’s will be by using WIS 20.

This Week:

  1. Sidewalk by the cemetery and County ES intersection.

 

Next Week:

  1. Topsoiling/grading

 

WIS 20 – County L to WIS 83 (Waterford) Traffic:

  1. Access to Bower’s Produce can be made by continuing east on WIS 20 from County L (East Troy)
  2. Access to Green Meadows can be made by going west on WIS 20 from WIS 83 (Waterford)
  3. Access to Witte Landscaping can be made by going west on WIS 20 from WIS 83 (Waterford)

 

This Week:

  1. Completed Patching operations
  2. Shoulder widening
  3. Began paving from the CN Railroad to WIS 83
  4. Milling operations removing the top 2” of asphalt

 

Next Week:

  1. Complete asphalt paving from CN Railroad going east to WIS 83.
  2. Complete milling operations near WIS 83, then go from County L to Bell School Rd.

 

Long Term (2+weeks)

  1. Reopen the I-43 Ramps (Tentatively late the week of September 9th).
  2. Begin working on retaining wall by the county line.
  3. Begin paving from County L to Bell School Rd

Information on the other WisDOT project up on I-43 from US 12 to WIS 83 is below:

https://projects.511wi.gov/12rock/

 

Information on the US 12 project between Elkhorn and WIS 20:

https://projects.511wi.gov/12elkhorn/

 

 

If you do not want to receive these updates, please let me know and I can remove you from the distribution list. Also, WisDOT has a project website set up for information that is more general than this email but could be useful if needed. https://projects.511wi.gov/20wal/