Generic selectors
Exact matches only
Search in title
Search in content
Post Type Selectors

Construction Update WIS 20: CONSTRUCTION UPDATE WIS 20-We were able to snag a traffic control crew a day early and they have been working removing equipment and preparing to reopen WIS 20. The crew should be completed with their work in the next few hours and then WIS 20 will be reopened from East Troy to Waterford!Thank you all for your patience and understanding as this was a lengthy project and a lot of work to get done!

Construction Update WIS 20

Work between County L and WIS 83 picked up this week with the patching operations. All the patches are completed in the WIS 20 WB lanes, and we will continue working on the WIS 20 EB lanes tomorrow and next week. Asphalt paving is schedule to being from the CN railroad tracks going east towards WIS 83 on Thursday next week.

 

The East Troy operations were slow this week, but sidewalk and restoration are scheduled for next week. The I-43 ramp reopening’s has been moved back a week to the week of September 9th due to pavement marking crew availability. We are trying to get the ramps opened as soon as possible but the weather in July caused delays on other projects and now those are getting caught back up.

 

WIS 20 (East Troy)

Traffic:

  1. Access to Bower’s Produce can be made by continuing east on WIS 20 from County L (East Troy)
  2. Access to Green Meadows can be made by going west on WIS 20 from WIS 83 (Waterford)
  3. Access to Culver’s will be by using WIS 20.

 

This Week:

  1. Electrical work

 

Next Week:

  1. Topsoiling/grading
  2. Sidewalk by the cemetery

 

WIS 20 – County L to WIS 83 (Waterford) Traffic:

  1. Access to Bower’s Produce can be made by continuing east on WIS 20 from County L (East Troy)
  2. Access to Green Meadows can be made by going west on WIS 20 from WIS 83 (Waterford)
  3. Access to Witte Landscaping can be made by going west on WIS 20 from WIS 83 (Waterford)

 

This Week:

  1. Patching operations (WIS 20 WB lane)
  2. Asphalt pavement to fill patches.

 

Next Week:

  1. Continue/complete patching operations. (WIS 20 EB Lane)
  2. Begin asphalt paving from CN Railroad going east to WIS 83.

 

Long Term (2+weeks)

  1. Reopen the I-43 Ramps (Week of September 9th).
  2. Begin working on retaining wall by the county line.

Information on the other WisDOT project up on I-43 from US 12 to WIS 83 is below:

https://projects.511wi.gov/12rock/

 

Information on the US 12 project between Elkhorn and WIS 20:

https://projects.511wi.gov/12elkhorn/

 

 

If you do not want to receive these updates, please let me know and I can remove you from the distribution list. Also, WisDOT has a project website set up for information that is more general than this email but could be useful if needed. https://projects.511wi.gov/20wal/