Construction Update WIS 20: CONSTRUCTION UPDATE WIS 20-We were able to snag a traffic control crew a day early and they have been working removing equipment and preparing to reopen WIS 20. The crew should be completed with their work in the next few hours and then WIS 20 will be reopened from East Troy to Waterford!Thank you all for your patience and understanding as this was a lengthy project and a lot of work to get done!

Construction Update WIS 20

All the asphalt was finished in the Village of East Troy this week with shouldering/curb backfill operations continuing.  Topsoiling and restoration will follow beginning next week. The pavement marking crews are scheduled for the week of the 8/26 so things are looking good for ramp openings around Labor Day (maybe before, likely shortly after the holiday).

 

WIS 20 between County L and WIS 83 will have a lot of activity going forward. We started patching operations and those will continue for the next few weeks, and we added extra drums and barricades between CTH L and Bell School Rd to help delineate the patch work and help reduce speeds.

 

WIS 20 (East Troy)

Traffic:

  1. Access to Bower’s Produce can be made by continuing east on WIS 20 from County L (East Troy)
  2. Access to Green Meadows can be made by going west on WIS 20 from WIS 83 (Waterford)
  3. Access to Culver’s will be by using WIS 20.

 

This Week:

  1. Completed HMA paving
  2. Backfilling curb/Shouldering
  3. Working on signal bases

 

Next Week:

  1. Topsoiling/grading
  2. Sidewalk by the cemetery

 

WIS 20 – County L to WIS 83 (Waterford) Traffic:

  1. Access to Bower’s Produce can be made by continuing east on WIS 20 from County L (East Troy)
  2. Access to Green Meadows can be made by going west on WIS 20 from WIS 83 (Waterford)
  3. Access to Witte Landscaping can be made by going west on WIS 20 from WIS 83 (Waterford)

 

This Week:

  1. Asphalt paved back the CN Railroad crossing.
  2. Began patching operations.

 

Next Week:

  1. Continue patching operations.

 

Long Term (2+weeks)

  1. Complete patching
  2. Begin asphalt milling operations (remove top 2”) and asphalt paving (put 2” back down of new pavement).

 

Information on the other WisDOT project up on I-43 from US 12 to WIS 83 is below:

https://projects.511wi.gov/12rock/

 

Information on the US 12 project between Elkhorn and WIS 20:

https://projects.511wi.gov/12elkhorn/

 

 

If you do not want to receive these updates, please let me know and I can remove you from the distribution list. Also, WisDOT has a project website set up for information that is more general than this email but could be useful if needed. https://projects.511wi.gov/20wal/