Construction Update WIS 20: CONSTRUCTION UPDATE WIS 20-We were able to snag a traffic control crew a day early and they have been working removing equipment and preparing to reopen WIS 20. The crew should be completed with their work in the next few hours and then WIS 20 will be reopened from East Troy to Waterford!Thank you all for your patience and understanding as this was a lengthy project and a lot of work to get done!

Construction Update WIS 20

The asphalt pavers are on site and hopefully will be completed early next week with the work in East Troy. While working on the County L intersection, there may be some delays while they work on paving the intersection (especially tomorrow morning). While things continue to advance in East Troy, we are looking to re-open the I-43 ramps the week of Labor Day (weather dependent and will keep updating as we move along).

 

WIS 20 between County L and WIS 83 will remain closed until sometime in October. A better date for that re-opening is hard to forecast because there are a lot of operations that need to be done in that stretch, but we will work to advance that schedule as much as possible.

 

WIS 20 (East Troy)

Traffic:

  1. Access to Bower’s Produce can be made by continuing east on WIS 20 from County L (East Troy)
  2. Access to Green Meadows can be made by going west on WIS 20 from WIS 83 (Waterford)
  3. Access to Culver’s will be by using WIS 20.

 

This Week:

  1. HMA paving
  2. Re-opened County ES

 

Next Week:

  1. Complete HMA paving
  2. Work on signal bases
  3. Topsoiling/grading

 

WIS 20 – County L to WIS 83 (Waterford) Traffic:

  1. Access to Bower’s Produce can be made by continuing east on WIS 20 from County L (East Troy)
  2. Access to Green Meadows can be made by going west on WIS 20 from WIS 83 (Waterford)
  3. Access to Witte Landscaping can be made by going west on WIS 20 from WIS 83 (Waterford)

 

This Week:

  1. Work around the CN crossing

 

Next Week:

  1. CN railroad completes their work, and we pave the asphalt to match in with WIS 20.

 

Long Term (2+weeks)

  1. Begin patching operations 8/19

 

Information on the other WisDOT project up on I-43 from US 12 to WIS 83 is below:

https://projects.511wi.gov/12rock/

 

Information on the US 12 project between Elkhorn and WIS 20:

https://projects.511wi.gov/12elkhorn/

 

 