Generic selectors
Exact matches only
Search in title
Search in content
Post Type Selectors

Construction Update WIS 20: CONSTRUCTION UPDATE WIS 20-We were able to snag a traffic control crew a day early and they have been working removing equipment and preparing to reopen WIS 20. The crew should be completed with their work in the next few hours and then WIS 20 will be reopened from East Troy to Waterford!Thank you all for your patience and understanding as this was a lengthy project and a lot of work to get done!

Construction Update WIS 20

Hello,

The County ES north leg work is ongoing, and the rough schedule outline below has been updated and on scheduled to re-open on Thursday (weather dependent).  WIS 20 between County L and WIS 83 is moving along as well. The CN railroad crossing work is scheduled for the week of August 4th with our work picking up once they are completed.

WIS 20 (East Troy)

Traffic:

  1. Access to Bower’s Produce can be made by continuing east on WIS 20 from County L (East Troy)
  2. Access to Green Meadows can be made by going west on WIS 20 from WIS 83 (Waterford)
  3. Access to Kwik Trip during the County ES closure will be using County ES coming from the Mukwonago direction (North).
  4. Access to Culver’s will be by using WIS 20.

This Week:

  1. Rock placement
  2. Curb and gutter installation
  3. Begin grading for asphalt next week

Next Week:

  1. Being asphalt paving
  2. Pavement Markings

County ES North Leg Closure (Tentative and very weather dependent)

  1. Asphalt paving (8/3 to 8/7)
  2. Pavement marking (8/8)
  3. Re-open on Thursday, 8/8

WIS 20 – County L to WIS 83 (Waterford) Traffic:

  1. Access to Bower’s Produce can be made by continuing east on WIS 20 from County L (East Troy)
  2. Access to Green Meadows can be made by going west on WIS 20 from WIS 83 (Waterford)
  3. Access to Witte Landscaping can be made by going west on WIS 20 from WIS 83 (Waterford)
  4. Once the guardrail is removed on WIS 20 along Honey Creek/County Line area, the barricades on either side of the “Fully Closed” section will be tightly closed as the roadway is no longer safe to allow vehicles through (other than EMS).
  5. CN railroad crossing is scheduled for the week of August 4th.

This Week:

  1. Finish storm sewer

Next Week:

  1. Work around the CN crossing

Long Term (2+weeks)

  1. Begin patching operations around 8/12
  2. Begin asphalt paving once the CN railroad crossing is completed.

Information on the other WisDOT project up on I-43 from US 12 to WIS 83 is below:

https://projects.511wi.gov/12rock/

Information on the US 12 project between Elkhorn and WIS 20:

https://projects.511wi.gov/12elkhorn/

If you do not want to receive these updates, please let me know and I can remove you from the distribution list. Also, WisDOT has a project website set up for information that is more general than this email but could be useful if needed. https://projects.511wi.gov/20wal/