Construction Update WIS 20: CONSTRUCTION UPDATE WIS 20-We were able to snag a traffic control crew a day early and they have been working removing equipment and preparing to reopen WIS 20. The crew should be completed with their work in the next few hours and then WIS 20 will be reopened from East Troy to Waterford!Thank you all for your patience and understanding as this was a lengthy project and a lot of work to get done!

WIS 20 Construction Update 06/21/2024

Hello,
Work is ongoing in East Troy with storm sewer installation and hopefully being roadway excavation next week. There is heavy rainfall forecasted for this weekend so we will see what that does to the site and any schedule impacts. For the area between County L and WIS 83, there are cross culverts being installed and those will continue into next week.
WIS 20 (East Troy)
Traffic:
1) Access to Bower’s Produce can be made by continuing east on WIS 20 from County L (East Troy)
2) Access to Green Meadows can be made by going west on WIS 20 from WIS 83 (Waterford)
3) The area in front of Scot Industries where traffic goes on the gravel will be maintained to try and keep two lanes of traffic. This issue is the existing WIS 20 only has room for one lane, so we are trying to make that as useful as possible.
This Week:
1) Continue storm sewer installation
2) Crushing the old concrete road to be re-used as a foundation layer
Next Week:
1) Complete storm sewer installation
2) Complete concrete crushing
3) Begin roadway excavation
Long Term (2+weeks out)
1) The north leg of County ES 21-day closure is tentatively scheduled to begin around July 15th. As we get closer to the 4th of July, I will firm up that schedule more.
WIS 20 – County L to WIS 83 (Waterford)
Traffic:
1) Access to Bower’s Produce can be made by continuing east on WIS 20 from County L (East Troy)
2) Access to Green Meadows can be made by going west on WIS 20 from WIS 83 (Waterford)
3) Access to Witte Landscaping can be made by going west on WIS 20 from WIS 83 (Waterford)
This Week:
1) Begin Saw cutting operations
2) Begin installing cross culverts
Next Week:
1) Continue cross culverts
2) Complete the saw cut operations
Information on the other WisDOT project up on I-43 from US 12 to WIS 83 is below:
Information on the US 12 project between Elkhorn and WIS 20:
 
 
Thanks Brad, for your exceptional communication through out this project. 🙂