Construction Update WIS 20: CONSTRUCTION UPDATE WIS 20-We were able to snag a traffic control crew a day early and they have been working removing equipment and preparing to reopen WIS 20. The crew should be completed with their work in the next few hours and then WIS 20 will be reopened from East Troy to Waterford!Thank you all for your patience and understanding as this was a lengthy project and a lot of work to get done!

WIS 20 Weekly Construction Update

Hello,

 

With the weather finally letting up, the WIS 20 Stage 2 traffic implementation is ongoing and will be mostly completed today. Some minor work will continue tomorrow but traffic will be moved into their temporary home today until mid/late June according to the latest schedule update (weather dependent).  

 

The I-43 SB entrance and NB exit ramps will close today at some point, the official/signed detour is to use I-43 to get to WIS 83 and then come back to WIS 20 (see attachment). We will keep the message boards on I-43 to help alert drivers to the closure for the next week to help with the transition.   

 

This Week:

  1. See the Stage 2 Project Brief for a layout of what the traffic configuration will look like later today
  2. When Stage 2 is set up, the I-43 detour will be utilized as shown on the project brief.  

 

Next Week:

  1. Begin breaking and removing the old concrete roadway
  2. Install erosion control devices
  3. Begin storm sewer installation

 

Future Work (2 weeks+)

  1. Not much to add here, we will be removing the old road, installing storm sewer, and grading for the foreseeable future.

 

Thanks,

Brad