The concrete gained strength this week and the grading crews were on site today working on restoring behind the curb. They will finish up tomorrow and next week they will be preparing for the asphalt which is anticipated mid-week.
Roadway Schedule (Weather Dependent)
- Week of June 23 – Let concrete gain strength, topsoil/restoration (Ongoing, completed tomorrow)
- Week of June 30 – Grade the gravel, asphalt paving, install overhead sign
- Week of July 7 – Permanent signing and pavement marking.
Traffic:
- Access to Dollar General can be made by taking WIS 20 west across County ES, using the median opening for Shell/McDonalds/Culvers, and going west on the WIS 20 EB lanes.
- Access to Shell/McDonalds/Culverts can be made using WIS 20 west across County ES to the median opening for the left turn like the current configuration. There are other accesses off County ES as well that will stay open.
- Access to the Oak Ridge Cemetery is available by using WIS 20 WB lanes.
- The I-43/WIS 20 interchange will remain open
- County ES will remain open but the right turn lane for County ES SB to WIS 20 WB will close for sidewalk and grading.
Other nearby projects:
Information about the US 12 project between Whitewater and WIS 20/WIS 67: